Originally planned as two separate car parks it was decided by the design team to condense in one "super" car park as this made better use of the space available. DELTABEAM® was used as a slim floor solution adding an extra floor so maximising the number of bays that could be delivered.
This is the UK largest single DELTABEAM® project to date with around 900nr beams. For durability purposes all the beams were hot dipped galvanised to 140 microns. The installation period was planned to be over 12 months but was condensed to just nine months.
The perimeter beams were designed to included fixings to support the metal grill cladding. Peikko HPKM® Column Shoes & HPM® Anchor Bolts were used on the precast columns again helping to delivery the project ahead of schedule.